Timeline
Project timelines
Typically our remodeling schedule is booked about six months out. You should plan for a minimum of four months for design development and permitting, pending project size. Simple projects such as kitchen or bathroom remodels move fairly quickly because there is less design work and permits can be done over the counter. If you are remodeling more of your home including changing walls, adding square footage, etc., then you can assume design and permitting could take a year or more, pending which reviews are required by the city for your specific project.
200 sf full kitchen remodel with partial wall removal, all interior work.
Design and Permitting: 4 months | Remodeling : 4-6 months
500 sf basement master suite remodel, minor exterior changes, no digging/excavation.
Design and Permitting: up to 6 week| Remodeling: 7-9 months
750 sf attic remodel / vertical addition / new floor, exterior changes.
Design and Permitting: up to 6 week| Remodeling: 11-14 months
2000 sf whole home remodel, minor exterior changes.
Design and Permitting: up to 2 months | Remodeling: 11-14 months
NOTES
When you’re planning your project, keep in mind that this process as well as your project budget & schedule will be impacted by permits, historical regulations, code revisions and site inspections.
You can also contact us with any questions and we are happy to provide more information.